The concrete crew showed up this morning and began setting up. Before they arrived, I was out there even earlier to take care of some last minute things that I'd thought of during the night. I had just finished when the crew arrived.
The pumper truck showed up about 8:30 and the first concrete truck arrived around 9:00. The pour began soon after that.
I photographed and videoed progress during the day (http://www.flickr.com/photos/les_stockton/sets/72157625159403546/). And when all this was being scheduled, Rachel was a bit aggressive and arranged to have an electrician on-site to set up so that it would be easier to use a portable generator to supply a minimal amount of electricity directly to the house, rather than having to string extension cords through the door or through a dryer vent. We were successful on both projects.
Wednesday, October 13, 2010
Tuesday, October 12, 2010
2010.10.12 - Slab Preparation
was afraid that it wasn't going to happen, because we waited all day, but the concrete crew didn't come. Then they finally showed up around 17:30 and started putting down the moisture barrier, which went down quickly, and then they unloaded rebar and started cutting it and putting it into place.
The plan is to come in tomorrow morning, finish rebar in the patio (it got too dark to finish this evening), and to form up in a few places. The concrete will go in and they should have it all done tomorrow.
I took my phone camera out there and got a little bit of video (http://www.flickr.com/photos/les_stockton/sets/72157625028000063/with/5077151642/) of the work this evening.
The plan is to come in tomorrow morning, finish rebar in the patio (it got too dark to finish this evening), and to form up in a few places. The concrete will go in and they should have it all done tomorrow.
I took my phone camera out there and got a little bit of video (http://www.flickr.com/photos/les_stockton/sets/72157625028000063/with/5077151642/) of the work this evening.
Friday, October 8, 2010
2010.10.08 - Behind Schedule On Floors
Friday, Oct 8, 2010
I worked from home today. I walked the construction site while waiting for the concrete contractor to arrive. I shot a few photos of the place while walking between the house and my current house.
The concrete guys didn't show up, but they didn't bother to call until 17:00. By then, I kinda had it figured out, but I was glad to at least get the call. Most contractors wouldn't have even bothered to do that at the end of the day.
The current plan now is that they will prep the site on Monday (I hope they can get it all done in one day), and then pour concrete on Tuesday.
The concrete guys didn't show up, but they didn't bother to call until 17:00. By then, I kinda had it figured out, but I was glad to at least get the call. Most contractors wouldn't have even bothered to do that at the end of the day.
The current plan now is that they will prep the site on Monday (I hope they can get it all done in one day), and then pour concrete on Tuesday.
2010.09.10 - Back On Track
Friday, Sep 10, 2010
After a couple of months off, I'm back at it again. This time, my wonderful wife Rachel is helping me. The summer is almost over. The temperatures are cooler. The work is more pleasant. And it's not such a chore when there is more than one person working. I work well with her and I'm thankful to have her helping.
What we're doing now is preparing for the slab. I've done all the sub-floor utility work, and so now we just need to get things ready to pour a slab in the remaining 3 modules. I'll explain later why we do the slabs after the concrete walls and concrete ceiling.
In order to have a standard 4-inch thick slab, and have it cure uniformly, it's necessary to level the sand base for the concrete to be poured. This means setting up a laser level and then walking around the room with a stick (we're using a tamper that helps compact the sand, but has a line on it that we use to tell with the laser if we're low or high in that spot). We rake and/or shovel sand to low spots and rake off areas where it's too high. We're almost done.
As a re-cap, we got the slab in the garage poured a year or so ago. That allowed us to close in the garage and it has been a place that we could lock and secure building materials and tools for the rest of the construction. The remaining 3 modules had more utility work to be done, but we've gotten that done and now we're hoping to pour the remaining slabs in mid-October.
The reason we are doing the slabs now, rather than before the walls and roof were poured, is that with a concrete house, if we had poured the slabs first, then when we put the forms in to hold up the roof for pouring that concrete, the weight of the roof concrete would've definitely broken our slab. To prevent that the walls and roof are poured in one pour. The slabs are poured later.
Anyway, I hope that explains it. I hope to write more as we progress. We took a few photos. Rather than use my fancy camera, we just went in and took a few photos with our new phone cameras. I've posted a full set of photos on my flickr site.
What we're doing now is preparing for the slab. I've done all the sub-floor utility work, and so now we just need to get things ready to pour a slab in the remaining 3 modules. I'll explain later why we do the slabs after the concrete walls and concrete ceiling.
In order to have a standard 4-inch thick slab, and have it cure uniformly, it's necessary to level the sand base for the concrete to be poured. This means setting up a laser level and then walking around the room with a stick (we're using a tamper that helps compact the sand, but has a line on it that we use to tell with the laser if we're low or high in that spot). We rake and/or shovel sand to low spots and rake off areas where it's too high. We're almost done.
As a re-cap, we got the slab in the garage poured a year or so ago. That allowed us to close in the garage and it has been a place that we could lock and secure building materials and tools for the rest of the construction. The remaining 3 modules had more utility work to be done, but we've gotten that done and now we're hoping to pour the remaining slabs in mid-October.
The reason we are doing the slabs now, rather than before the walls and roof were poured, is that with a concrete house, if we had poured the slabs first, then when we put the forms in to hold up the roof for pouring that concrete, the weight of the roof concrete would've definitely broken our slab. To prevent that the walls and roof are poured in one pour. The slabs are poured later.
Anyway, I hope that explains it. I hope to write more as we progress. We took a few photos. Rather than use my fancy camera, we just went in and took a few photos with our new phone cameras. I've posted a full set of photos on my flickr site.
Subscribe to:
Posts (Atom)